Demo CI Job Structure: Accept Barrier + Concurrency Group Over Job Consolidation

Context and Problem Statement

demo-integration.yml runs 7 demo scenarios and 7 invariant-harness jobs as two GitHub Actions matrix blocks. The invariant-harness job declares needs: demo, which — per GitHub Actions semantics — creates a full fan-in barrier: every invariant job must wait for the slowest of all 7 demo jobs before any invariant job can start. The actual logical dependency is pairwise (fv-invariant depends only on fv-demo, not on fvcv-handoff-demo), so the barrier introduces systematic lag proportional to the variance in demo scenario runtimes.

Three structural options were evaluated for eliminating or reducing this lag.

Decision Drivers

  • DEMOCI-04-001: invariant failures MUST produce a separate, independent pass/fail status on the PR, visible even when the demo job fails.
  • DEMOCI-02-011: the workflow MUST define a concurrency group to cancel superseded PR runs — this is an unimplemented MUST already in spec.
  • Workflow maintainability: the YAML must remain easy to add new scenarios to.
  • GitHub Actions platform constraints: needs: on a matrix job name waits for all entries of that matrix, with no native pairwise-dependency syntax.

Considered Options

  • Option A — Merge demo + invariant into one job per matrix entry (single 13-step matrix job that runs both the demo and pytest inline)
  • Option B — Expand to 14 named jobs (replace both matrix blocks with 14 individually-named jobs so each invariant job can needs: its specific demo job by name)
  • Option C — Accept barrier, add concurrency group (keep the current two-matrix structure; implement the already-specified DEMOCI-02-011 concurrency block that was never wired in; eliminate the pairwise ordering problem by cancelling superseded PR runs early)

Decision Outcome

Chosen option: Option C — Accept barrier, add concurrency group, because:

  • Option A violates DEMOCI-04-001: merging both steps into one job collapses the two independent pass/fail statuses into one. A reviewer can no longer distinguish "demo passed, invariant failed" from "demo failed" — exactly the failure mode that motivated the separate-job design.
  • Option B achieves pairwise ordering but multiplies YAML maintenance cost 14×. Every new scenario requires two new named jobs; the YAML grows non-linearly and there is no matrix inheritance to DRY it. Additionally, even with named pairwise needs:, GitHub Actions does not guarantee that artifact uploads from a named job are visible to its dependent before the dependent starts; the download-artifact step already handles this correctly.
  • Option C recovers the most impactful practical improvement: on active PR branches, every push cancels the prior queued run, so the accumulated "all 7 demo jobs must finish before any invariant job starts" wall-clock cost only occurs once per PR commit, not for every intermediate push. The cancel-in-progress: false on main-branch runs preserves per-commit signals.

This decision is accepted-provisional because the scenario coverage split (minimum PR validation set vs. full post-merge set) is not yet designed or validated. When DEMOCI-06 is implemented — defining a minimum PR set and a full post-merge set — this ADR should be revised to reflect whether the reduced PR scenario set further mitigates the barrier impact.

Consequences

  • Good, because DEMOCI-02-011 (a MUST that was never implemented) is closed.
  • Good, because superseded PR runs are cancelled, recovering CI minutes on active branches and giving faster per-commit feedback.
  • Good, because the two-matrix structure is preserved and new scenarios require only two new matrix entries (one per block) per DEMOCI-03-004.
  • Good, because DEMOCI-04-001's separate pass/fail signals are fully preserved.
  • Neutral, because the fan-in barrier persists structurally on individual commits; it only manifests as lag when a PR push is not superseded by a later push.
  • Bad, because genuinely pairwise dependency cannot be expressed in GitHub Actions without Option B's YAML explosion.

Validation

The concurrency block (DEMOCI-02-011) is verifiable by inspection of demo-integration.yml. The behaviour (cancel superseded PR runs, never cancel main-branch runs) is validated by observing CI behaviour on a PR with multiple rapid pushes.

More Information

  • Source concern: CERTCC/Vultron#1967
  • Related implementation issue: CERTCC/Vultron#1862 (push-to-main trigger + concurrency + cache-warm removal)
  • DEMOCI spec: specs/demo-ci.yaml DEMOCI-02-011, DEMOCI-05
  • Follow-on: CERTCC/Vultron#1794 epic — scenario coverage analysis will determine whether a minimum PR validation set can reduce the number of matrix entries that participate in the barrier, further reducing worst-case lag.
  • Generated spec requirements: specs/demo-ci.yaml DEMOCI-06-001 through DEMOCI-06-003.

Amendment — 2026-08-24

The "never cancel on-main runs" policy (DEMOCI-02-014 as originally written, referenced in line 64 above) was superseded. cancel-in-progress is now the literal true on all triggers. Burst-merge throttling on main is handled instead by a 60-second debounce step (.github/actions/debounce-main-push) at the start of the scenarios job — rapid pushes cancel their sleeping predecessors, so only the last commit in a burst runs the full suite. Per-commit granularity was judged unnecessary: a time-range bisect across a typical 4–6 PR batch is sufficient to identify regressions. DEMOCI-02-013, DEMOCI-02-014, DEMOCI-02-015, and DEMOCI-05-002 in specs/demo-ci.yaml were updated accordingly.

Amendment — 2026-10-12

The status moved from accepted-provisional to accepted when its lifecycle epoch reached day 28 (ADR-0120, #4521). The reason given in Decision Outcome for the provisional status no longer holds: the scenario coverage split is designed and built (DEMOCI-06). The minimum PR set and the full post-merge set are resolved from .github/demo-scenarios.json by the scenarios job in .github/workflows/demo-integration.yml, and the coverage matrix is in notes/demo-ci-scenario-coverage.md. The barrier decision stands with the reduced PR set.